May 15, 2026

We filed 15-year resource plan with Minnesota regulators

On May 15, 2026, we filed our 2027–2041 Integrated Resource Plan (IRP) with the Minnesota Public Utilities Commission, outlining how we plan to meet customers’ electricity needs over the next 15 years.

“Our responsibility is to deliver cost-effective, reliable electricity to our customers,” said President Todd Wahlund. “This plan reflects the decisions we find best meet those expectations over the long term.”

The plan includes proposals to add a 50-megawatt natural gas plant expected to be in service in 2031–2032 and two 50-MW wind projects expected in service in 2035 and 2040.

The proposed additions are intended to help us meet electricity demand and maintain system reliability.

The IRP also reflects projects in development following our last Resource Plan approval, including the 50-MW Solway Solar expected to be in service in 2026, the 295-MW Abercrombie Solar expected to be in service in 2028, a 75-MW battery storage facility, and additional wind generation.

We develop our resource plans using forecasts for customer demand, available generation resources, and market conditions across its service territory. The Minnesota Public Utilities Commission will review the plan through a regulatory process that includes opportunities for public and stakeholder input. We expect to file a separate IRP in North Dakota in 2027. South Dakota does not currently have an IRP requirement.

“Resource planning is an ever-evolving process,” said Wahlund. “We’ll continue to monitor issues that may impact our plan as we continue our commitment to providing reliable and affordable electricity to our customers.” 

You can track the filing on the MPUC's website Submission 20265-231860 · eFiling