The schedules in these tables do not include sales tax, adjustments, or riders, which may vary by month and state. For complete terms and other rates, such as outdoor lighting, farm service, or irrigation, see rates, rules, and regulations. Charges apply monthly.
Rate codes: 404—secondary; 405—primary; 408—nonmetered (closed)
This schedule is applicable to both single- and three-phase non-residential customers with demands below 20 kilowatt (kW) and to residential customers with three-phase service only with demands below 20 kW. This schedule is not applicable to dusk to dawn outdoor lighting.
404: Secondary Service; 405: Primary Service
Please note that Minnesota and North Dakota schedule 408: Non-metered service - Secondary only-1000 Watts or less - is closed to new installations.
During a rate review an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
404 and 405 Customer charge |
$18.50 | $24.90 | $20.00 |
408 Customer charge |
$5.50 | NA | NA |
Monthly minimum | Customer + Facilities Charge | Customer Charge | Customer Charge |
Facilities | $0.00 | NA | NA |
404 Kilowatt-hour charge June - September |
7.546¢ | 6.682¢ | 6.820¢ |
404 Kilowatt-hour charge October – May |
5.595¢ | 4.521¢ | 4.614¢ |
405 Kilowatt-hour charge June - September |
7.329¢ | 6.440¢ | 6.572¢ |
405 Kilowatt-hour charge October-May |
5.471¢ | 4.331¢ | 4.420¢ |
408 Kilowatt-hour charge June - September |
7.546¢ | 6.681¢ | NA |
408 Kilowatt-hour charge October - May |
5.595¢ | 6.681¢ | NA |
Download | Download | Download |
Rate codes: 401—secondary; 403—primary
This schedule is applicable to three-phase residential customers, and both single- and three-phase non-residential customers, with a measured demand of at least 20 kilowatts (kW) during the most recent 12 months. This schedule is not applicable for dusk to dawn outdoor lighting.
Low load factor demand charges only apply to customers that have both a metered demand of 200 kW or greater and a monthly load factor of 15% or less.
During a rate review an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Secondary Service (401) | |||
Customer charge | $39.00 | $31.90 | $25.00 |
Facility charge | $1.50/kW of annual maximum demand (minimum 20 kW) |
98¢/kW of annual maximum demand (minimum 20 kW) |
$1.00/kW of annual maximum demand (minimum 20 kW) |
Minimum bill | Customer + Facilities + Demand Charges |
Customer + Facilities Charges | Customer + Facilities + Demand + Low Load Factor Charges |
Kilowatt-hour charge June - September |
4.644¢ | 7.506¢ | 3.393¢ |
Kilowatt-hour charge October - May |
5.272¢ | 5.078¢ | 3.363¢ |
Demand charge per kilowatt June - September |
$2.00 (minimum 20 kW) | NA | $3.60 (minimum 20 kW) |
Demand charge per kilowatt October - May |
$1.00 (minimum 20 kW) | NA | $2.18 (minimum 20 kW) |
Low load factor per kilowatt per month |
NA | NA | $3.54/kW |
Primary Service (403) | |||
Customer charge | $26.00 | $21.30 | $20.00 |
Facility charge | $1.01/kW of annual maximum demand (minimum 20 kW) |
65¢/kW of annual maximum demand (minimum 20 kW) |
67¢/kW of annual maximum demand (minimum 20 kW) |
Minimum bill | Customer + Facilities + Demand Charges |
Customer + Facilities Charges | Customer + Facilities + Demand + Low Load Factor Charges |
Kilowatt-hour charge June - September |
4.581¢ | 7.233¢ | 3.282¢ |
Kilowatt-hour charge October - May |
5.184¢ | 4.865¢ | 3.235¢ |
Demand charge per kilowatt June - September |
$1.92 (minimum 20 kW) | NA | $3.46 (minimum 20 kW) |
Demand charge per kilowatt October - May |
$.97 (minimum 20 kW) | NA | $2.08 (minimum 20 kW) |
Low load factor per kilowatt per month |
NA | NA | $3.54/kW |
Download | Download | Download |
Rate code: 708
This schedule is applicable to nonresidential customers with one meter providing electrical service with a measured demand of at least 20 kW within the most recent 12 months. This rate has three time-of-use price periods that vary by state and by season. Billing demand is based on the highest demand registered over any one hour during the month.
Review the full schedule for information about declared-peak notifications.
During rate reviews an interim rate adjustment may apply to the charges below.
Minnesota |
North Dakota |
South Dakota | |
---|---|---|---|
Customer charge | $59.00 | $219.00 | $200.00 |
Monthly minimum | Customer + facilities + demand charges |
Customer + facilities charges | Customer + facilities + demand + low load factor demand charges |
Facilities charge | $2.12/kW per annual max kW (min 20 kW) |
98¢/kW per annual max kW (min 20 kW) |
$1.00/kW per annual max kW (min 20 kW) |
Energy charge per kilowatt-hour |
|||
Declared-peak June - September |
79.499¢ | 43.264¢ | 28.829¢ |
Declared-peak October – May |
22.768¢ | 16.259¢ | 30.322¢ |
Intermediate June - September |
3.395¢ | 2.571¢ | 3.236¢ |
Intermediate October – May |
3.632¢ | 2.638¢ | 3.206¢ |
Off-peak June - September |
2.350¢ | 1.702¢ | 2.163¢ |
Off-peak October – May |
2.948¢ | 1.845¢ | 2.277¢ |
Demand charge per kilowatt |
|||
Declared-peak June - September |
NA | $0.00 | $0.00 |
Declared-peak October – May |
NA | $0.00 | $0.00 |
Intermediate June - September |
$2.92 | $3.44 | $4.67 |
Intermediate October – May |
$4.44 | $5.12 | $2.84 |
Off-peak June - September |
$0.00 | $0.00 | $0.00 |
Off-peak October - May |
$0.00 | $0.00 | $0.00 |
Download | Download | Download |
Rate codes: 602, 603, 632
These are standard, non-controlled rates for non-residential customers.
During a rate review an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
603 - Secondary Service |
|||
Customer charge | $93.00 | $215.90 | $215.90 |
Facilities charge | $1.03/kW <1000 kW 67¢/kW >= 1000 kW per annual max kW per month (min 80 kW) |
76¢/kW <1000 kW 56¢/kW >= 1000 kW per month (min 80 kW) |
77¢/kW <1000 kW 57¢/kW >= 1000 kW per month (min 80 kW) |
Monthly minimum | Customer + facilities + demand charges |
Customer + facilities + demand charges |
Customer + facilities + demand charges |
Billing demand per kilowatt June - September |
$13.99 (min 80 kW) | $10.75 (min 80 kW) | $10.84 (min 80 kW) |
Billing demand per kilowatt October - May |
$11.25 (min 80 kW) | $8.54 (min 80 kW) | $6.64 (min 80 kW) |
Excess billing demand | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand shall be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. |
Kilowatt-hour charge June - September |
2.590¢ | 2.286¢ | 2.291¢ |
Kilowatt-hour charge October - May |
2.950¢ | 2.341¢ | 2.271¢ |
602 - Primary Service |
|||
Customer charge | $253.00 | $282.00 | $282.00 |
Facilities charge | 49¢/ kW of annual max demand per month (min 80 kW) |
48¢/kW of annual max demand per month (min 80kW) |
49¢/kW of annual max demand per month (min 80 kW) |
Monthly minimum | Customer + facilities + demand charges |
Customer + facilities + demand charges |
Customer + facilities + demand charges |
Billing demand per kW June - September |
$13.64 (min 80 kW) | $10.35 (min 80 kW) | $10.39 (min 80 kW) |
Billing demand per kW October - May |
$10.89 (min 80 kW) | $8.15 (min 80 kW) | $6.34 (min 80 kW) |
Excess billing demand | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand shall be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. |
Kilowatt-hour charge June - September |
2.230¢ | 2.224¢ | 2.219¢ |
Kilowatt-hour charge October - May |
2.530¢ | 2.264¢ | 2.187¢ |
632 - Transmission Service |
|||
Customer charge | $253.00 | $282.00 | $282.00 |
Facilities charge | $0.00/ kW | $0.00/ kW | $0.00/ kW |
Monthly minimum | Customer + facilities + demand charges (min 80 kW) |
Customer + facilities + demand charges (min 80 kW) | Customer + facilities + demand charges (min 80 kW) |
Billing demand per kW June - September |
$12.74 (min 80 kW) | $8.85 (min 80 kW) | $8.50 (min 80 kW) |
Billing demand per kW October - May |
$9.97 (min 80 kW) | $7.30 (min 80 kW) | $4.24 (min 80 kW) |
Excess billing demand | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand shall be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. |
Kilowatt-hour charge June - September |
2.010¢ | 2.103¢ | 2.119¢ |
Kilowatt-hour charge October - May |
2.200¢ | 2.121¢ | 2.070¢ |
Download | Download | Download |
Rate codes: 610, 611, 639
This rate schedule is applicable for monthly billing to nonresidential customers with measured demand of at least 80 kW within the most recent 12 months. This rate has three time-of-day price periods that vary by state and by season.
During rate reviews an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | ||
---|---|---|---|---|
611 - Secondary Service |
||||
Customer charge | $102.00 | $215.90 | $215.90 | |
Facilities charge | 76¢/kW <1000 kW 57¢/kW >= 1000 kW per annual max kW (min 80 kW) |
76¢/kW <1000 kW 57¢/kW >= 1000 kW per annual max kW (min 80 kW) |
76¢/kW <1000 kW 57¢/kW >= 1000 kW per annual max kW (min 80 kW) |
|
Monthly minimum | Customer + facilities charges | Customer + facilities + demand charges |
$325.00 + customer + facilities charges |
|
Excess billing demand | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | |
Energy charge per kilowatt-hour | ||||
On-Peak June-September |
3.600¢/kWh | 3.527¢/kWh | 3.480¢/kWh | |
On-Peak October-May |
3.460¢/kWh | 3.090¢/kWh | 2.946¢/kWh | |
Shoulder June-September |
3.120¢/kWh | 2.683¢/kWh | 2.651¢/kWh | |
Shoulder October-May |
3.170¢/kWh | 2.753¢/kWh | 2.628¢/kWh | |
Off-peak June-September |
1.600¢/kWh | 1.776¢/kWh | 1.772¢/kWh | |
Off-peak October-May |
1.840¢/kWh | 1.925¢/kWh | 1.866¢/kWh | |
Demand charge per kilowatt | ||||
On-Peak June-September |
$11.65/kW | $7.31/kW | $7.42/kW | |
Peak October-May |
$8.63/kW | $5.29/kW | $3.80/kW | |
Shoulder June-September |
$2.34/kW | $3.44/kW | $3.42/kW | |
Shoulder October-May |
$2.62/kW | $3.25/kW | $2.84/kW | |
Off-peak June-September |
$0.00/kW | $0.00/kW | NA | |
Off-peak October-May |
$0.00/kW | $0.00/kW | NA | |
610 - Primary Service |
||||
Customer charge | $273.00 | $282.00 | $282.00 | |
Facilities charge | 48¢/kW per annual max demand (min 80 kW) |
48¢/kW per annual max demand (min 80 kW) |
48¢/kW per annual max demand (min 80kW) |
|
Monthly minimum | Customer + facilities charges | Customer + facilities + demand charges |
$325.00 + customer + facilities charges |
|
Excess billing demand | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. |
Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | |
Energy charge per kilowatt-hour | ||||
On-Peak June-September |
3.310¢/kWh | 3.422¢/kWh | 3.351¢/kWh | |
On-Peak October-May |
3.140¢/kWh | 2.981¢/kWh | 2.821¢/kWh | |
Shoulder June-September |
2.890¢/kWh | 2.612¢/kWh | 2.562¢/kWh | |
Shoulder October-May |
2.900¢/kWh | 2.665¢/kWh | 2.526¢/kWh | |
Off-peak June-September |
1.500¢/kWh | 1.738¢/kWh | 1.721¢/kWh | |
Off-peak October-May |
1.700¢/kWh | 1.871¢/kWh | 1.800¢/kWh | |
Demand charge per kilowatt | ||||
On-Peak June-September |
$11.19/kW | $7.05/kW | $7.12/kW | |
On-Peak October-May |
$8.34/kW | $5.03/kW | $3.62/kW | |
Shoulder June-September |
$2.45/kW | $3.29/kW | $3.27/kW | |
Shoulder October-May |
$2.55/kW | $3.12/kW | $2.72/kW | |
Off-peak June-September |
$0.00/kW | $0.00/kW | NA | |
Off-peak October-May |
$0.00/kW | $0.00/kW | NA | |
639 - Transmission Service |
||||
Customer charge | $273.00 | $282.00 | $282.00 | |
Facilities charge | 0¢/kW of annual max demand (min 80 kW) |
0¢/kW of annual max demand (min 80 kW) |
0¢/kW of annual max demand (min 80 kW) |
|
Monthly minimum | Customer + facilities charges |
Customer + facilities + demand charges (min 80 kW) |
$325.00 + customer + facilities charges |
|
Excess billing demand | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. |
Demand may be increased 1 kW for each whole 10 kVar of measured reactive demand in excess of 50% of the metered demand in kW. | |
Energy charge per kilowatt-hour |
||||
On-Peak June-September |
2.810¢/kWh | 3.213¢/kWh | 3.146¢/kWh | |
On-Peak October-May |
2.640¢/kWh | 2.775¢/kWh | 2.626¢/kWh | |
Shoulder June-September |
2.490¢/kWh | 2.465¢/kWh | 2.418¢/kWh | |
Shoulder October-May |
2.500¢/kWh | 2.494¢/kWh | 2.364¢/kWh | |
Off-peak June-September |
1.250¢/kWh | 1.653¢/kWh | 1.637¢/kWh | |
Off-peak October-May |
1.450¢/kWh | 1.760¢/kWh | 1.694¢/kWh | |
Demand charge per kilowatt |
||||
On-Peak June-September |
$10.87/kW | $6.11/kW | $5.71/kW | |
On-Peak October-May |
$7.71/kW | $4.58/kW | $2.75/kW | |
Shoulder June-September |
$1.87/kW | $2.74/kW | $2.79/kW | |
Shoulder October-May |
$2.26/kW | $2.72/kW | $1.49/kW | |
Off-peak June-September |
$0.00/kW | $0.00/kW | NA | |
Off-peak October-May |
$0.00/kW | $0.00/kW | NA | |
Download Time of day chart |
Download Time of day chart |
Rate codes: 618, 620
This rate schedule is designed to enable the company to respond to potential customers by providing rate quotes and final rates based on a rate formula reviewed by Commission staff.
Application: This rate schedule is applicable to greenfield customers who reasonably demonstrate to the company:
(1) An expected metered demand of at least 25 MW at a single metering point,
(2) An expected load factor of at least 80%, and
(3) An expected annual energy sales of at least 175,000 MWhs over 12 consecutive billing months.
Customers will meet the above criteria to obtain and maintain service on this rate. Customers served on this rate who do not meet the above criteria will be moved to the most applicable rate schedule.
This schedule is not applicable for energy for resale. Emergency and supplementary/standby service will be supplied only as allowed by law.
The company requires a written electric service agreement (ESA) between the company and the customer. The company will file the customer’s executed ESA as a contract with deviations for Commission approval.
Rate determination: The rate specified in each customer's ESA shall be based upon and reflect either the marginal unit costs expected during the effective rate period or the marginal unit costs plus an appropriate margin determined on a case-by-case basis.
Review the applicable rate schedule for full details.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Rate schedule | Download | Download | Download |
Rate codes: MEITA, 690, 691, 692
Minnesota offers an Energy Intensive, Trade-Exposed (EITE) Rider exemption that provides a discount per kilowatt-hour equivalent to the EITE surcharge rate to customer account(s) granted exemption by the Commission from EITE costs pursuant to Minn. Stat. 216B.1696, Subd. 2(d).
The EITE Surcharge Rate is shown below and is detailed in Minnesota rate schedule section 13.09.
South Dakota offers an Economic Development Rate Rider that makes available through a customer's contract a discount from the company's applicable standard tariff (10.03 or 10.05), plus applicable riders. The discount will follow the Commission-approval process.
Application: This rider is applicable to the following:
(i) Greenfield customers with: Expected metered demand of at least 500 kW at a single metering point, and seasonal load factor that is above the seasonal system average load factor and above the seasonal class average load factor corresponding to existing customers under the otherwise applicable standard tariff.
(ii) Existing customers with: Metered demands of at least 1,000 kW that increase measured demand by at least 500 kW at a single new metering point, and seasonal load factor above the seasonal system average load factor and above the seasonal class average load factor under the otherwise applicable standard tariff.
For full details refer to South Dakota rate schedule section 14.13.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Discount surcharge | $0.00039 | N/A | TBD by contract |
Download | Download |
Rate codes: 185 (185P—penalty), 190 (190P—penalty)
This is for permanently connected interruptible heating loads with an alternate fuel backup system that's served with self-contained (typical) metering. You also may include water heaters on this rate when other interruptible load is in use. Heating loads may be controlled up to 24 hours a day and water-heating loads may be controlled up to 14 hours a day. Rate 185 allows for air-source heat pump loads to be cycled 15 minutes on and 15 minutes off during summer control periods.
During rate reviews an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Customer charge | $6.00 | $8.50 | $10.00 |
Monthly minimum bill | Customer + facilities charges |
Customer + facilities charges |
Customer + facilities charges |
Facility charge | $10.50 | $11.70 | $9.50 |
Kilowatt-hour charge June - September |
2.738¢ | 0.911¢ | 1.222¢ |
Kilowatt-hour charge October - May |
2.341¢ | 0.850¢ | 1.024¢ |
Penalty charge /kWh June-September |
63.450¢ | 41.350¢ | 26.749¢ |
Penalty charge /kWh October-May |
15.853¢ | 17.038¢ | 17.205¢ |
Download | Download | Download |
Rate codes: 165 (165P—penalty), 170 (170P—penalty); 168C, 169C
This tariff is for permanently connected interruptible heating loads with an alternate fuel backup system that's serviced by current transformer (CT) metering. You also may include water heaters on this rate when other qualified interruptible load is in use. Heating loads may be controlled up to 24 hours a day and water heating loads may be controlled up to 14 hours a day. The tariff does allow for short-duration cycling of qualified summer-season loads during control periods. To accommodate system controls Option 2 permits up to 5% of off-peak-load use to remain in service during control periods. The penalty provision of the tariff is not intended as a buy-through option.
During rate reviews an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Option 1 |
|||
Customer charge | $24.04 | $20.20 | $15.00 |
Monthly minimum bill | Customer + facilities charges |
Customer + facilities charges |
Customer + facilities charges |
Facilities charge | 45.0¢/kW of annual max. demand per month |
76.0¢/kW of annual max. demand per month |
50.0¢/kW of annual max. demand per month |
Kilowatt-hour charge June - September |
1.867¢ | 1.064¢ | 1.192¢ |
Kilowatt-hour charge October - May |
1.597¢ | 1.009¢ | 0.999¢ |
Penalty charge/kWh June - September |
63.450¢ | 41.350¢ | 26.749¢ |
Penalty charge/kWh October - May |
15.853¢ | 14.322¢ | 17.205¢ |
Option 2 |
|||
Customer charge | $20.00 | $20.20 | $15.00 |
Monthly minimum bill | Customer + facilities charges |
Customer + facilities charges |
Customer + facilities charges |
Facilities charge | 50.0¢/kW of annual max. demand per month |
76.0¢/kW of annual max. demand per month |
50.0¢/kW of annual max. demand per month |
Kilowatt-hour charge June - September |
2.509¢ | 1.064¢ | 1.481¢ |
Kilowatt-hour charge October - May |
1.871¢ | 1.009¢ | 1.219¢ |
Control period demand charge June- September |
$13.99/kW | $11.30/kW | $10.84/kW |
Control period demand charge October - May |
$11.25/kW | $8.49/kW | $6.64/kW |
Download | Download | Download |
Rate codes: 195 (195P—penalty), 197 (197P—penalty)
This rider is for both residential and non-residential service to any approved permanently connected deferred loads. Such loads primarily are thermal storage, like underfloor heating or central-storage furnaces, and may include water heaters and heat pumps when heat storage is also in use. Loads may be controlled up to 14 hours a day, as measured from midnight to midnight. Optional rate 195 allows for qualified summer-season loads such as a heat pump to be cycled 15 minutes on and 15 minutes off during control periods.
During a rate review an interim rate adjustment may be applied to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Customer charge | $11.00 | $8.80 | $8.50 |
Monthly minimum bill | Customer + facilities charges |
Customer + facilities charges |
Customer + facilities charges |
Facilities charge | $11.00 | $11.60 | $11.00 |
Kilowatt-hour charge June - September |
3.468¢ | 2.602¢ | 2.406¢ |
Kilowatt-hour charge October - May |
3.603¢ | 2.371¢ | 2.192¢ |
Penalty charge June - September |
44.913¢ | 35.916¢ | 26.749¢ |
Penalty charge October - May |
14.085¢ | 16.537¢ | 17.205¢ |
Download | Download | Download |
Rate code: 301 (301P—penalty)
This is for permanently connected deferred loads with self-contained (typical) metering, primarily thermal-storage space heating or cooling, and other approved loads. Energy is delivered between 10:00 p.m. and 6:00 a.m. All other hours of electric service are unauthorized and subject to penalty period kilowatt-hour charges. Penalty rates are not intended as buy-through options.
During a rate review an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Customer charge | $9.00 | $6.70 | $6.70 |
Monthly minimum bill | Customer + facilities charges |
Customer + facilities charges |
Customer + facilities charges |
Facilities charge | $6.00 | $6.00 | $6.00 |
Kilowatt-hour charge June - September |
1.032¢ | 1.439¢ | 0.968¢ |
Kilowatt-hour charge October - May |
1.109¢ | 1.591¢ | 1.014¢ |
Penalty charge/kWh June - September |
6.485¢ | 6.736¢ | 6.081¢ |
Penalty charge/kWh October - May |
4.271¢ | 4.602¢ | 4.761¢ |
Download | Download | Download |
Rate code: 302 (302P—penalty)
This is for permanently connected deferred loads with current transformer (CT) metering, primarily thermal-storage space heating or other approved loads. Energy is delivered between 10:00 p.m. and 6:00 a.m. All other hours of electric service are unauthorized and subject to penalty period kilowatt-hour charges. Penalty rates are not intended as buy-through options.
During rate reviews an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Customer charge | $9.00 | $6.70 | $6.70 |
Monthly minimum bill | Customer + facilities charges |
Customer + facilities charges |
Customer + facilities charges |
Facilities charge | $32.00 | $38.00 | $32.00 |
Kilowatt-hour charge June - September |
1.032¢ | 1.439¢ | 0.968¢ |
Kilowatt-hour charge October - May |
1.109¢ | 1.591¢ | 1.014¢ |
Penalty charge/kWh June - September |
6.485¢ | 6.736¢ | 6.081¢ |
Penalty charge/kWh October - May |
4.271¢ | 4.602¢ | 4.761¢ |
Download | Download | Download |
Rate code: 303 (303P—penalty)
This is for permanently connected deferred loads with primary current transformer (CT) metering served at primary voltage. Loads are thermal-storage space heating or cooling and other approved loads. Energy is delivered between 10:00 p.m. and 6:00 a.m. All other hours of electric service are unauthorized and subject to penalty period kilowatt-hour charges. Penalty rates are not intended as buy-through options.
During a rate review an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Customer charge | $9.00 | $6.70 | $6.70 |
Monthly minimum bill | Customer + facilities charges | Customer + facilities charges | Customer + facilities charges |
Facilities charge | $16.00 | $18.00 | $16.00 |
Kilowatt-hour charge June - September |
1.028¢ | 1.433¢ | 0.964¢ |
Kilowatt-hour charge October - May |
1.104¢ | 1.585¢ | 1.010¢ |
Penalty charge/kWh June - September |
6.485¢ | 6.736¢ | 6.081¢ |
Penalty charge/kWh October - May |
4.271¢ | 4.602¢ | 4.761¢ |
Download | Download | Download |
Rate codes: 760, 762
This tariff is available to residential customers on the Residential Service, RDC, or Farm Service Rates; and to commercial customers on the Small General Service Rate (less than 20 kW) and the General Service Rate. Participating eligible commercial customers may receive a monthly bill credit for each ton of connected cooling load.
Central cooling equipment will be cycled on a 15-minute on / 15-minute off schedule. Commercial customer dual stage air conditioners will be allowed to have the first stage run without interruption while the second stage will be shut off for the entire load management period.
Monthly bill credit may be prorated and applies June through September. Air conditioning may be cycled a maximum of 300 hours during the cooling season. During rate reviews an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Residential Monthly Credit June - September | $8.25 | $8.25 | $8.25 |
Commercial Monthly Credit Per Ton June - September | $6.00 | $6.00 | $6.00 |
Download | Download | Download |
Rate code: 191
This rate applies to water heaters that are metered separately and subject to controlled service. Water heaters may be controlled up to 14 hours a day.
During a rate review an interim rate adjustment may apply to the charges below.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Customer charge | $5.75 | $4.00 | $4.00 |
Monthly minimum bill | Customer + facilities charges | Customer + facilities charges | Customer charge |
Facilities charge | $0.00 | $2.00 | $2.00 |
Kilowatt-hour charge June - September |
3.084¢ | 3.078¢ | 2.442¢ |
Kilowatt-hour charge October - May |
3.204¢ | 2.661¢ | 2.097¢ |
Download | Download | Download |
Rate code: 192
Customers on base residential, farm, or general commercial tariffs may receive a bill credit each month when direct control to water heating is configured. Water heaters may be controlled up to 14 hours a day.
Minnesota | North Dakota | South Dakota | |
---|---|---|---|
Monthly Bill Credit | $10.00 | $8.00 | $8.00 |
Download | Download | Download |
For more details on rates and regulations concerning your electric service contact our Customer Service Center or download the full text of our rates.